Brine Schedule

Following are tentative dates for brine applications, depending on weather and scheduling with townships and brine companies. 

 

These could be postponed by 2-3 weeks:

2018 Brine Schedule by Township

 

Following are TENTATIVE dates for brine applications.  Dates may change due to weather and scheduling with contractors.

First application for all townships has been completed.

 

Berlin                    1st app                 early June                           05/29/18                             

    2nd app                late July

 

Boston                  1st app                 mid May                              05/18/18

    2nd app                mid July

    3rd app                September (twp appr)

 

Campbell             1st app                 mid May                              05/24/18                             

   2nd app                mid July

   3rd app                mid August

 

Danby                   1st app                 early May                            05/16/18             

    2nd app                late June

    3rd app                late August

 

Easton                  1st app                 early May                            05/18/18             

    2nd app                late June

    3rd app                twp approval

 

Ionia                      1st app                 mid May                              05/10/18             

    2nd app                mid July

    3rd app                twp approval

 

Keene                   1st app                 early June                           06/14/18                             

    2nd app                twp approval

 

Lyons                    1st app                 early June                           06/05/18             

    2nd app                mid August

 

N. Plains               1st app                 early June                           06/11/18             

    2nd app                twp approval

 

Odessa                 1st app                 mid June                              06/18/18                             

    2nd app                mid August

 

Orange                 1st app                 mid June                              06/12/18                             

    2nd app                mid August

 

Orleans                1st app                 late May                              05/30/18             

   2nd app                mid July

   3rd app                twp approval

 

Otisco                   1st app                 late May                              06/07/18             

2nd app                mid July

3rd app                twp approval

 

Portland               1st app                 early May                            06/01/18

    2nd app                early July

    3rd app                twp approval

 

Ronald                  1st app                 mid May                              05/23/18             

    2nd app                mid July

    3rd app                twp approval

 

Sebewa                1st app                 early June                           05/15/18